6.4.1
Connect a short length of hose from the Manual Water Level Test/ Drain [56] into a bucket. 
Open the Manual Water Level Test/ Drain [56]
Connect the Filling Loop [54] to the Filling Point [9]
Open the Manual Air Vent [6] - during filling, this should be shut if water is expelled.
Slowly Open the Isolating Valve on the Filling Loop, and the unit will start to fill. 
Fill until water is discharged via the Manual Water Level Test/ Drain [56].
6.4.2 Excess water should be drained off via the Manual Water Level Test / Drain.
Any water discharged into the Overflow Chamber [8] should be drained off from drain [66].
Disconnect and cap the Filling Loop [54].
6.5 Check that all air locks in the Primary System are cleared properly, and all Radiators bled.
7 COMMISSIONING.
7.1 Set the Heat Bank Thermal Store Pump to speed 2.
7.2 Turn on the electrical supply.
7.3 Bleed all pumps as described.
7.4 Run through the operation of the system as follows:
7.4.1 Set the programmer to Hot Water ON.
7.4.2 The boiler should fire, and the primary pump turn on. Within a short time (3 minutes) the flow from the boiler should feel hot to the touch. Check that the pipework to the primary coil is also hot. The flow to the central heating should not be hot at this stage.
7.4.3 Set the Programmer to Heating ON. The flow to the heating circuit should now get hot.
7.4.4 Turn off both the Hot Water and Heating on the Programmer. The Boiler should stop firing, and the primary pump stop - on systems where the boiler uses a pump over-run, the pump may not turn off for a few minutes.
7.4.5 Bleed the entire system to remove air.
7.4.6 Turn the Hot Water ON to allow the cylinder to fully recover. As it does, adjust the Balancing Valve on the Flow (or return) to the Primary Coil to obtain a temperature difference of approximately 10°C (or as specified in the Boiler Installation Instructions) between the Boiler Flow & Return.
7.4.7 Once the cylinder has recovered, check that hot water is available at all outlets.